1. Project Core Challenges
Xiangtang substation is a key power hub connecting multiple 110kV &35kV power nodes in Lanzhou Honggu District. The expansion project needed synchronous laying for multi-loop cross-section cables inside compact indoor cable duct rooms. Key construction pain points: Limited indoor working space forbids bulky heavy machines; synchronous laying for multiple parallel cables required uniform traction speed to avoid cable twisting; frequent short-distance shifting of laying positions led to low efficiency of traditional fixed conveyors.

2. APEX Customized Product & Service Solution
APEX’s core matching product is Tank900 intelligent remote-controlled cable conveyor, equipped with flexible crawler chassis for easy indoor relocation, intelligent grouping frequency conversion to realize synchronous speed for multi-machine linkage; supporting mini SA-QY-50 hydraulic tensioner for vertical high-floor cable pulling. Pre-sales technical team finished on-site duct measurement and customized grouping parameter setting within 3 working days; on-site after-sales engineers stayed for 15 days to guide equipment debugging and operator training. All machines pass ISO9001 & CE certification for stable indoor continuous operation.

3. Final Project Outcomes
Tank900’s movable design cut equipment relocation time per working point by 70%; multi-unit intelligent linkage eliminated cable twisting risk completely; multi-circuit synchronous cabling efficiency improved by 40%, the whole expansion cable construction completed ahead of plan, winning positive evaluation from State Grid Lanzhou Power Supply Company’s engineering department.

Please submit the form below. Your download will start automatically after successful submission.